![]() |
|
||||||||||
|
|
|
||||||||||
![]() |
|||||||||||
|
Case Study
|
Rehabilitation of Gurva Griha of Shree Jagannath Temple, Puri
RENOVATION OF THE GURVA GRIHA OF SHRI JAGANNATH TEMPLE The Gurva Griha or the holy sanctum of Lord Jagannath of Puri is having cantiver stone corbels in all the three floors. The stones in the corbels are stitched together in plan by grought iron dowels. These dowels over the years have got badly corroded and have cracked the existing corbel stones due to expansion resulting in progressive failure of these stones causing imminent danger to the deities and the pilgrims visiting the holy sanctum. The basic conditions of the original stones also become suspect due to weathering effect of the marine atmosphere. An expert committee was formed to evaluate the condition of the structure and suggest remedial measures. The committee was formed consisting of specialist from archeological survey of India, noted historians specialising in Orissa temp,e architecture, senior engineers from PWD Orissa , IIT Kharagpur, few selected specialized private organisation having experience and expertise in this field etc... The recommendation of the expert committee was in two parts that is on structural strengthening and on preservation. Details of structural strengthening are provided below. Structural Strengthening The floors work as horizontal diaphragms in a vertical tower and are necessary for providing stiffness lateral forces that is earth quake, wind etc. In the ground floor at the base the inside dimensions are 8.85 m x 8.85 m, there are six rows of corbels each of 466mm high and 370 mm cantilever projection. On this, four wrought iron beams carry the floor stones with a total thickness of 950 mm. These beams are assumed to be going inside the main walls. The load transference, is through the beams,to corbels and finally to the main walls. It was found necessary of strength the corbel action by strengthening the joints between the corbels by means of P.M.C grouts and also to eliminate local failure by introducing a stainless steel truss to support the corbel stones. The corbel stones were planned to be stitched together by means of threaded stainless steel bars inserted into the drilled holes and grouted with Epoxy Resins would be able to lock the corbels into the temple main walls and the pressure from the expanding rusting dowels would be neutralized. For preservation of original stones, two phase strategy was formulated i.e., to provide a preservative coating on the outside stone surface to retard the process of ageing, in the second phase the phase 1 activities are completed and the P.M.C. grout formulation used on each batch, by Contract Division was : Pagel = 25 kg Tapecrete P 151 = 6.0kg Water = 7 to 8 litres. Total P.M.C. grout consumed in three floors of Gurva Griha is around 28 tonnes. |
||||||||||
|
|||||||||||